Tilbury LNG Expansion Project
Nextgen was responsible for the Protection & Control and Telecommunications design of the new 69/13.8kV Tilbury Substation for the FortisBC Tilbury LNG project. We also designed, fabricated and shop tested the P&C panels for the project. Nextgen continued to be involved as the project transitioned out of the design phase by managing and preforming all commissioning activities for the Tilbury Substation. This included:
Overall Commissioning Management including development of and adherence to the Commissioning Plan, Commissioning Test Summary and approved Test Sheets
Equipment Testing & Commissioning
Communications, Protection & Control Commissioning
Construction support
Project handover
Operator training
Nextgen continues to support the Tilbury Substation through operations, maintenance and training activities.